CHANNEL RESTORATION IN AN URBAN SALMONID
STREAM (CONT.)
Figure 5 and 6. Modified Live Siltation and
Pole Planting typical biotechnical drawings (Bio Draw 1.0).
Watershed Restoration students constructed four “modified
live siltation” structures. Modified live siltation
is a revegetation technique intended to encourage deposition
at the inner bend of a channel and aid in the formation of
point bars. Additionally, individual student projects
were designed and implemented using techniques the students
learned in class. These bioengineering projects included
a brush mattress, a brush box, and the installation of biodegradable
erosion blankets, which were through-planted with Carex spp.
(basket sedge) transplants.
The earthwork for the project was completed within two weeks
during the month of October, 1999. The project reach
remained dry and the work was completed before the expected
November rains. Approximately 900 cm of material was
removed from the sandbar and used to reconstruct the right
bank. During the excavation of the sandbar, which was
thought to be the location of the original stream channel,
old spawning gravel was uncovered and left in the newly exposed
streambed.
REVEGETATION PLAN
The reconstructed right bank and other areas that were disturbed
needed ground cover for erosion control and stabilization.
The area needing seed, mulch, and revegetation with native
species was approximately .15 ha. The majority of the
area was seeded at 45 kg/ha with the native grass Blue Wildrye
(Elymus glaucus). Blue wildrye is a fast growing bunchgrass
with a large, deep root system. This cool-season grass
begins new growth in the fall, even before the rains begin.
Blue wildrye is an excellent grass for reseeding burned and
disturbed areas. The area was seeded with other grasses
native to the Arboretum such as Slender Hairgrass (Deschampsia
elongata). Certified weed-free wheat straw mulch was
applied at a rate of approximately 3750 kg/ha (1 ½
tons/ac) and at a depth of 30-40 cm.
After the initial seeding of native grass species for erosion
control, SWAG and the Arboretum sponsored several community-oriented
“planting days”. On one of these “planting
days” over 80 community members volunteered. These
volunteer crews planted native grass plugs and native riparian
and upland species that were donated from the Arboretum and
local agencies.
Figure 7 and 8. Before and After. The
left photo shows the channel before reconstruction.
The right photo shows the channel shortly after project
completion, with volunteers planting riparian vegetation.
A 10-ft swath of fill soil directly under (parallel to) some
areas on the right bank only received seed and mulch.
These areas will later be built up using soil wraps, or filled
and graded to a slope consistent with the natural contours
of the streambank. Brushlayers of willow and cottonwood
species will be placed between soil layers as the bank is
constructed to add further soil stabilization. Once
this upper portion of the right bank is completed, native
tree species such as valley oaks may be planted here to eventually
provide an overhead canopy that will shade this stream reach.
PREVIOUS PAGE
NEXT PAGE
|